|
“Check the equipment prior
to storage to anticipate any possible problems at the time of
installation. You can minimize installation problems by
checking sizes, design features called for on the plans and
specifications and all interface components”
The proper installation of a submersible wet well pumping
station involves careful coordination from planning through
completion. Deliveries must be scheduled and checked. All
accessories must be installed in accordance with the job
specifications and the manufacturers’ instructions. Electrical
control panels must be installed and tested with care. When
start-up is accomplished properly, the specifier, operator and
owner can be assured of trouble-free operation. Careful
preparation and planning is needed to ensure proper
installation of all equipment in submersible sewage pumping
stations. There must be effective coordination between the
supervising engineer, the mechanical and electrical
contractors, and all suppliers.
The first step is to ensure that the required station
equipment is ordered completely and accurately according to
specifications, and that—considering lead times—all of it will
arrive prior to the scheduled installation. This includes not
only the pump and electrical control panel, but the station
itself (if prefabricated) and all accessories, such as piping,
valves and access covers.
Receipt and Inspection
All equipment should be examined upon receipt for any signs of
apparent damage. If there is damage, a claim should be filed
immediately with the carrier and the supplier should be
notified. All parts shipped loose or separately should be
checked for loss or damage.
If the equipment won’t be installed immediately, it is best to
store it in a clean, dry location where it will be protected
from possible damage. Follow the manufacturer’s
recommendations and protect equipment from low temperatures or
freezing. Check the equipment prior to storage to anticipate
any possible problems at the time of installation. You can
minimize installation problems by checking sizes, design
features called for on the plans and specifications and all
interface components.
Handling Pumps
“A submersible pump should be transported and stored in
accordance with the manufacturer’s recommendations”
Make sure that it cannot roll or fall over. Always lift the
pump by its carrying handle, never by the motor cable.
In the absence of specific manufacturer recommendations about
storage, pumps must be protected against excessive moisture
and heat. This precaution is necessary to prevent moisture
damage to internal components and the power cord, etc. The
impeller should be rotated by hand occasionally (for example,
every other month) to ensure free movement of the rotating
elements. The cable entry seal must conform to the outside
diameter of the cable to prevent leakage into the pump.
The end of the power cable must not be submerged, as water may
wick through the cable into the motor.
After any period of storage, the pump should be inspected,
tested and/or reconditioned in accordance with the
manufacturer’s recommendations before it is put into
operation.
Pump Station Installation
When beginning the installation, ensure that all equipment
is on site and that all manufacturer instructional literature
is available, has been reviewed and is followed.
In addition to the pump(s), the following items are typically
required:
• Discharge elbow/support base and/or sealing arrangement for
connecting the pump to the discharge line.
• Guide rail(s) consisting of specified material and size.
• Upper guide rail brackets for attaching the rail(s) to the
access cover frame or top of the station.
• Intermediate guide rail supports as required.
• Specified discharge piping and fittings.
• The proper check and shut-off valves.
• Level sensor or other control equipment.
• Cable holder for level sensors or other sensor brackets.
• Junction box or conduit box (if required).
• Access frame (with covers).
• Control panel.
Access Cover Installation
There are two common installation methods for access
covers. One is to cast the unit into the poured concrete slab
well cover. The other method is to frame flange the unit and
drop it into the steel well cover.
Both types of installation must align properly with the
baseplate. Prior to casting the door unit into concrete, the
cover should be closed and checked to make certain that it
rests on the frame all around. Shim the frame as necessary to
ensure proper door closure. Remember that aluminum frames must
be protected from the wet concrete by a bituminous coating.
Internal Assembly
Now that the access cover is in the proper position, you
can begin to install the internal station components.
Place the pump discharge connection in position. Temporarily
secure the guide rail(s) in the upper mounting brackets and
the discharge bosses at the bottom. Install the intermediate
support brackets, if required. Ensure the rails are in a true
vertical position, so the pump will clear the access opening
and slide freely down the rails into place in the discharge
connection.
Once the rails are in proper alignment, bolt the discharge
connection into the floor of the station. Connect the
discharge pipe to the discharge connection and proceed to
install the check valve, shutoff valve and fittings according
to the plans and specifications.
All level-sensing devices must be properly secured to the
access cover frame or the wet well. Install them at the levels
indicated on the plans and specifications. Control components,
other than level-sensing devices, should not be installed in
the wet well.
Lifting equipment is normally required for handling pumps. It
should be able to hoist a pump straight up and down in the
station, preferably without having to reset the lifting hook.
Make certain the lifting equipment is securely anchored. Keep
all personnel out from under suspended loads.
Before lowering a pump into place, it must be checked for
correct rotation, using one of the following methods:
1. Prior to installation in the wet well, lay the pump on its
side and momentarily run (jog) and check it for rotation. When
running the pump outside the wet well, care must be taken to
stay clear of the impeller and to provide a safe, temporary
connection of the motor leads. The best procedure is to lift
the pump with a hoist or tilt it slightly and observe the
rotation. An arrow on the pump casting, or instructions in the
Pump Instruction and Operation Manual (IOM), will show the
proper
direction of rotation. This is the most accurate method to
test for proper rotation; however, other methods are
usually provided as a secondary check or for circumstances
when the pump cannot be lifted from the station.
2. After installation, if the check valve has an external
operating arm, you should be able to see which rotation of the
motor opens the check valve widest. This indicates the higher
flows, and is the correct rotation for the pump.
3. If pressure taps are available, rotation can be ascertained
by reading the shut-off head on a pressure gauge. The proper
rotation will produce the higher pressure.
4. The least desirable procedure is to position the pump in
the hand mode, using the Hand-Off-Automatic (HOA) switch,
lower it to the bottom of the wet well, and check the drop in
water level in the well. The rotation resulting in the faster
drawdown is the proper rotation.
Use the above procedures before start-up of the station. Keep
in mind that visual inspection of the rotating elements is the
most accurate method.
The direction of rotation on three-phase pumps may be changed
by interchanging any two motor leads at their control panel
connections. For single-phase pumps, if improper rotation is
observed, consult the IOM or contact the pump manufacturer.
After the proper rotation is verified, lower the pump along
the guide rail(s). Upon reaching its bottom position, it
should automatically connect to the discharge. Adjust as
required, following the manufacturer’s recommendations.
Fasten the lifting chain on the access frame eyebolt and
fasten the cables on the cable holder. Cable supports are
required for deep installations. Run the pump and level
control cables up to the electric control panel or into the
junction box, if used.
The pump and level control cables should be long enough to
reach the control panel without splicing. If a junction box,
conduit box or quick connector plugs are utilized, they should
be located outside the wet well—or, if located in the wet
well, be of at least NEMA Type 4 construction.
It is highly recommended that conduit seal-offs be located
between the wet well and the control panel to prevent gas
migration into the control panel enclosure.
Arrange for a cable, if needed, between the sump and the
electrical control panel. Make sure the cables are not sharply
bent or pinched, and that all connections are sealed and
watertight to prevent leakage from ground water.
Control Panels
Before making a new installation, a qualified electrician
or factory service technician should verify the horsepower,
voltage rating and full load amperage of each pump. This
information should be used to ensure that the control panel is
of the correct horsepower, and that the heater coils furnished
in each motor starter overload unit are sized or set correctly
to match the motor’s operating current as given on the motor
nameplate.
The service voltage and frequency should be checked to ensure
they are the same as the motor rating. This information should
be used to cross-check the circuit breakers, fuse or
disconnect ratings. All electrical work must comply with
national and local codes and regulations.
At the time of installation, the panel or equipment should be
checked for missing or loose components—including a correct
wiring diagram. All wire terminations should be checked for
tightness. Care must be taken in handling the control panel
and equipment during installation to avoid damage to the
enclosure or any of its components.
Location and provisions for mounting the panel should be shown
on the plans for the job. Make certain the enclosure is the
type specified for that particular location. Adequate racks,
mounting brackets, and fastening hardware must be used to
securely mount the panels and devices.
On flat surfaces, panels should have a slight clearance
between the back of the panel and the mounting surface to
enable air circulation. While clearance is usually provided by
the enclosure design, it may need to be furnished by mounting
hardware. This ensures heat dissipation and prevents moisture
accumulation.
If the panel is mounted on a rack, it must be constructed and
braced to provide a flat, rigid surface that will not distort
the panel and cause possible door alignment problems.
Mounting bolts and hardware must be of sufficient size to
provide stable positioning and of materials suitable for the
operating environment.
Field Wiring
All conduits and wires must be installed as required on
the plans for the specific job. All cable entrances into the
enclosure must be in accordance with the NEC, and shall
maintain the integrity of the NEMA enclosure, to prevent
intrusion of moisture, dust and gas vapors. When possible,
conduits should be attached from the bottom of the enclosure
to facilitate weatherproofing. Weatherproof hubs and sealed
fittings should be used.
The size of conduits and wires must be adequate for the
specific requirements of the incoming service, pump motor
leads and remote control devices. The NEC must be used as a
minimum guideline.
After the installation of the conduit and wiring, make certain
that all terminations in the control panel conform to the
panel manufacturer’s diagrams and instructions. The incoming
service voltage must be correct for the panel. Typically,
three-phase systems are designed for a 208, 240, 480, or 575
volt, four-wire service voltage. Single phase systems are most
often 208 or 240 volt, two- or three-wire, but are sometimes
120-volt, two-wire service voltage.
As a safety precaution, before connecting the motor leads to
the control panel or applying power to the pump, take and
record megohm readings with a 500-volt megger. Connect all
motor leads together and check the combination to ground. The
readings should be above 20 megohms at all points. A motor
should not be run if any reading is below 10 megohms. If this
is the case, find and correct the source of the low readings.
If the readings are between 10 and 20 megohms, the pump should
be run for short periods and the readings rechecked. Only
after tests are complete should the motor leads be connected
permanently to the control panel.
The pump leads must now be connected to the control panel
following the panel diagram, using the pump manufacturer’s
wiring diagram to distinguish and verify the connection and
color coding of the leads. Internal pump/motor safety controls
should be identified following the pump manufacturer’s wiring
diagram and connected to the panel as specified by the panel
manufacturer. Make certain the pump is correctly grounded.
If automatic control of the pumps is provided by liquid level
sensors in the wet well, all connections must be made to the
proper terminal points in the control panel. Care must be
taken to identify each sensor and its specific function.
Proper connections ensure sequential and automatic operation
of the pumps.
Wires must be marked to provide future identification should
re-connection be required during maintenance or
troubleshooting. A record should be made in the permanent file
for the control panel regarding field wire connections, wire
sizes and types, cable lengths and any other related
information. This file can be valuable during normal
maintenance, for emergency situations and as a reference for
future installations.
When incoming service voltage is available and the system is
complete and ready to be put into service, a qualified
electrician should be present. If the service voltage is
240-volt, three-phase, four-wire from Delta-connected
transformers, the "high line" must be identified; it has a
higher than 120 volt (usually about 210 volt) reading phase to
neutral. The control panel must then be checked to make
certain no control circuits or 120 volt operating devices are
connected to this incoming high line.
Some local codes require that the high line be on a particular
phase connection, usually Phase B or sometimes Phase C.
(Consult local codes to determine if there is such a
requirement in your area.) Most control panels are designed to
use Phase A for all 120 volt phase to neutral circuits when no
control transformer is used.
Start-Up and Testing
Many pump and panel manufacturers have special forms that can
be used during the start-up of the station (Figs. 1 and 2).
Some manufacturers require that these forms be filled out and
returned to ensure warranty on the pumps, control panels and
station components. This type of form provides a detailed
description of the procedures and tests to be performed.
Following is a summary of these procedures.
The panel is ready to be put into service after the incoming
service voltage has been checked on the line side of the main
circuit breaker or disconnect, and it is verified that all
phases and neutral (if used) are present and at acceptable
levels.
All circuit breakers and selector switches must be in the off
position. The main circuit breaker or disconnect can then be
turned on. One at a time, each of the other circuit breakers
should be turned on, to check the load side of each for
correct voltage. This includes the control circuit.
With sufficient water in the well, turn each pump operating
selector switch Hand-Off-Automatic (HOA) to the hand position
to run each pump. Take and record amperage readings on each
motor lead with a clamp-on ammeter. The phase-to-phase voltage
must be checked and recorded at this time. If there is
excessive amperage draw on one leg, start troubleshooting by
checking the manufacturer’s recommendations. Consult with the
power company only after all other checks have been made.
The initial readings for amperage, voltage and ohmmeter
resistance, plus megohm readings, should be the start of a
permanent maintenance file. Monthly, quarterly or annual
readings should be taken as part of a good preventive
maintenance program. They are the basis for scheduled checks,
which can indicate the trend of the motor current draw and can
help prevent major outages and costly motor rewind jobs.
Operational Checks
When start-up and testing is completed, the system is ready to
be checked for automatic operation. Both or all of the pump
operating selector switches should be turned to the auto
position, and the alarms turned on or reset as required for
normal operation.
The best way to check and correctly set the on and off levels
is to provide an external water supply source to fill the wet
well to various predetermined levels. This water can be from a
nearby hydrant or other source. Care should be taken when
discharging water into the wet well not to affect floats or
other controls. By controlling the fill and then observing or
setting the operating points, the automatic cycle or cycles of
operation can be checked, no matter what type of level
controls are employed.
To achieve second and/or subsequent pump start levels, the
circuit breaker or disconnect can be turned off for the lead
pump. This enables the wet well to fill, without running the
lead pump, to the lag pump on level for checkout.
All pumps may be turned off to enable checking and testing of
alarm levels. The pumps should be permitted to pump, to allow
checking of the desired off level. If a low alarm level is
included below the normal off level, a pump may have to be run
in the hand mode to check it. If guaranteed submergence with
redundant low water cutoff is specified, it should be checked
to be sure the wiring has eliminated the possibility of hand
operation. The control system should be cycled more than once
to check the proper and automatic alternation sequence of the
pumps. If the panel is supplied with a manual alternator
switch, it should be operated and the pumps cycled again to
check for sequencing. Each run cycle, after alternation,
should be checked to run both lead, lag and any subsequent
pumps to ensure complete, correct alternation of the duty
cycle.
Simulation Testing
Simulation testing should be done only in those extreme
cases where sufficient water is not available and the pump(s)
cannot be run in the well. Because the pump(s) are not run and
the actual well water level is not used to energize the level
sensing devices, the procedure is not recommended.
Other Checks
During the check-out of control systems, check the pump
run pilot light indicators, elapsed time meters and any other
associated controls for proper operation. The alarm levels,
when activated, should operate all devices in the system.
These can include an alarm light, pilot light, audible horn or
bell and a relay to provide remote signal contacts or
telemetering contacts.
All the alarm devices should be checked for proper operation,
including audible alarm silencing circuits or switches and any
reset pushbutton, if used.
If any special control or alarm
features are included in the system, they should be checked by
simulation if actual conditions cannot be achieved. These may
include seal failure indicators, motor thermal sensors or
telemetered incoming or outgoing signals.
Another device often used and not always checked is the phase
monitor. Most have three functions: loss or low voltage on a
single phase, loss or low voltage on all three phases, and
phase rotation reversal.
By turning off the service voltage to the panel, disconnecting
one of the sensing leads to the phase monitor, and then
insulating it when the power is turned back on to the panel,
the pumps should not operate in either the hand or automatic
mode. Reversing the above procedure, the lead should then be
reconnected. This will check the loss of a single phase
feature.
On some units, if the service nominal voltage is low enough,
the set point on the monitor can be raised sufficiently above
nominal voltage to cause the running pump or pumps to drop
out. This will check the three phase low voltage setting of
the phase monitor.
By turning off the service voltage and reversing two of the
sensing leads on the phase monitor (to induce improper
rotation), and then restoring the service voltage, the pumps
should not operate in either the hand or automatic mode.
Reversing the above procedure, the leads should then be
reconnected. This will check the phase reversal feature of the
phase monitor.
These checks are important, since they offer the protection
needed during normal operation of the system. The last is
important if the service is ever disconnected and reconnected,
to prevent the pumps from being run in reverse rotation. If a
station is provided with a power plug for the use of a
portable standby generator, this reverse phase feature is
essential to ensure that the generator phase rotation is
matched with the normal service phase rotation.
Final Tests
After the above tests have been completed, the panel
should be thoroughly checked to ensure that all wires have
been reconnected properly, all switches or jumpers used for
simulations have been removed, and all circuits restored to
normal operation.
With the service voltage turned off, all wire terminations
should be rechecked for tightness and the panel cleaned to
ensure a good, maintainable environment. The panel should now
be ready for continuous automatic operation.
The run time on elapsed time meters should be read and
recorded for each pump. These readings should be the start of
a permanent maintenance file. Periodic readings should be
taken and recorded as part of a good preventive maintenance
program.
With these readings, the alternating duty cycles can be
checked to ensure operation of the alternator. Many pump and
motor maintenance schedules are based on hours of operation.
Actual automatic cycles are monitored to be sure they are not
excessive. For submersible motors, a maximum of 10 to 15
starts per hour are acceptable in terms of equipment life.
Over a period of time, this record may show system demand
trends and indicate the need for larger pumps. By calculating
the pumping rate of each pump and the hours of run time, the
gallons of water pumped for a given time period can be
estimated. This can indicate problems with increased water
infiltration into the system due to cracked or broken lines,
based on an increase in gallons pumped with no other
substantial changes within the system.
Make periodic checks during the first few days of operation of
a new system. This can uncover unforeseen problems and help
the operator become familiar with duty cycles and other
characteristics of the pumping station. This special attention
can help avoid future problems.
Source – Engineering Review
For any further queries with reference to the article
write to
shirish@engrreview.com
|